Installation of the Laptop Docking Station (LDS)
TASK 46-26-34-400-001-A
Installation of the Laptop Docking Station (LDS)
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 46-26-34-861-051-A ** ON A/C NOT FOR ALL Subtask 46-26-34-865-051-A ** ON A/C NOT FOR ALL
Subtask 46-26-34-420-050-A ** ON A/C NOT FOR ALL
Subtask 46-26-34-862-051-A ** ON A/C NOT FOR ALL Subtask 46-26-34-860-052-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.04.02 06:26:09 UTC
Installation of the Laptop Docking Station (LDS)
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| FOR [39TA1] (DOCKING STATION-EFB LAPTOP) | ||
| No specific | Torque wrench: range to between 0.48 and 0.37 m.daN (42.48 and 32.74 lbf.in ) ![]() | |
| FOR [39TA2] (DOCKING STATION-EFB LAPTOP) | ||
| No specific | Torque wrench: range to between 0.48 and 0.37 m.daN (42.48 and 32.74 lbf.in ) ![]() | |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 122 | AVIONICS COMPARTMENT |
| 212 | COCKPIT |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-41-00-861-002-A | Energize the Aircraft Electrical Circuits from the External Power |
| TASK 24-41-00-861-002-A-01 | Energize the Aircraft Electrical Circuits from the APU |
| TASK 24-41-00-861-002-A-02 | Energize the Aircraft Electrical Circuits from Engine 1(2) |
| TASK 24-41-00-862-002-A | De-energize the Aircraft Electrical Circuits Supplied from the External Power |
| TASK 24-41-00-862-002-A-01 | De-energize the Aircraft Electrical Circuits Supplied from the APU |
| TASK 24-41-00-862-002-A-02 | De-energize the Aircraft Electrical Circuits Supplied from the Engine 1(2) |
| FOR [39TA1] (DOCKING STATION-EFB LAPTOP) | |
| TASK 20-28-00-912-802-A | Electrical Bonding - General Maintenance Procedure |
| FOR [39TA2] (DOCKING STATION-EFB LAPTOP) | |
| TASK 20-28-00-912-802-A | Electrical Bonding - General Maintenance Procedure |
Subtask 46-26-34-861-051-A ** ON A/C NOT FOR ALL Subtask 46-26-34-865-051-A ** ON A/C NOT FOR ALL
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
4. Procedure| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| FOR FIN: 40TA1 (DUEFB) | |||
| 122VU | EFB/CAPT | 41TA1 | U08 |
| FOR FIN: 40TA2 (DUEFB) | |||
| 49VU | EFB/F/O | 41TA2 | H09 |
Subtask 46-26-34-420-050-A ** ON A/C NOT FOR ALL
A. Installation of the EFB LDS
(1) FOR [39TA2] (DOCKING STATION-EFB LAPTOP)
(a) Install the F/O EFB LDS (11) in position with the eight washers (10) and screws (9).
(b) Prepare for electrical bonding (Ref. AMM TASK 20-28-00-912-802).
(c) TORQUE the screws (9) to between 0.48 and 0.37 m.daN (42.48 and 32.74 lbf.in )
.
(d) Push the harnesses P2 (2),P3 (5) and P1 (6) inside the lateral console.
(e) Connect the connector P2 (2).
(f) Install the plate (4) with the six screws (3).
(g) Get access to the Avionics Compartment.
(h) Connect the connectors P3 (5) and P1 (6).
(2) FOR [39TA1] (DOCKING STATION-EFB LAPTOP)
(a) Install the CAPT EFB LDS (11) in position with the eight washers (10) and screws (9).
(b) Prepare for electrical bonding (Ref. AMM TASK 20-28-00-912-802).
(c) TORQUE the screws (9) to between 0.48 and 0.37 m.daN (42.48 and 32.74 lbf.in )
.
(d) Push the harnesses P2 (1),P3 (7) and P1 (8) inside the lateral console.
(e) Connect the connector P2 (1).
(f) Install the plate (4) with the six screws (3).
(g) Get access to the Avionics Compartment.
(h) Connect the connectors P3 (7) and P1 (8).
Subtask 46-26-34-865-052-A ** ON A/C NOT FOR ALL (1) FOR [39TA2] (DOCKING STATION-EFB LAPTOP)
(a) Install the F/O EFB LDS (11) in position with the eight washers (10) and screws (9).
(b) Prepare for electrical bonding (Ref. AMM TASK 20-28-00-912-802).
(c) TORQUE the screws (9) to between 0.48 and 0.37 m.daN (42.48 and 32.74 lbf.in )
. (d) Push the harnesses P2 (2),P3 (5) and P1 (6) inside the lateral console.
(e) Connect the connector P2 (2).
(f) Install the plate (4) with the six screws (3).
(g) Get access to the Avionics Compartment.
(h) Connect the connectors P3 (5) and P1 (6).
(2) FOR [39TA1] (DOCKING STATION-EFB LAPTOP)
(a) Install the CAPT EFB LDS (11) in position with the eight washers (10) and screws (9).
(b) Prepare for electrical bonding (Ref. AMM TASK 20-28-00-912-802).
(c) TORQUE the screws (9) to between 0.48 and 0.37 m.daN (42.48 and 32.74 lbf.in )
. (d) Push the harnesses P2 (1),P3 (7) and P1 (8) inside the lateral console.
(e) Connect the connector P2 (1).
(f) Install the plate (4) with the six screws (3).
(g) Get access to the Avionics Compartment.
(h) Connect the connectors P3 (7) and P1 (8).
B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
5. Close-up| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 49VU | EFB/F/O | 41TA2 | H09 |
| 122VU | EFB/CAPT | 41TA1 | U08 |
Subtask 46-26-34-862-051-A ** ON A/C NOT FOR ALL Subtask 46-26-34-860-052-A ** ON A/C NOT FOR ALL
B. Aircraft Maintenance Configuration
(1) Make sure that the work area is clean and clear of tools and other items.
(1) Make sure that the work area is clean and clear of tools and other items.
Illustration of the Laptop Docking Station (LDS)